Investor feasibility study · October 2026
Greek Real Estate Investment Venture: Feasibility Study
Prepared by Paschalis Filios
For prospective investors and partners · October 2026
Via WhatsApp +30 690 884 7300 · or email
Section 01
Executive summary
The opportunity. Greek apartment prices fell by 42.4% between the Q3 2008 peak and the Q3 2017 low. Since 2018 they have recovered strongly: the Bank of Greece index is up 93.9% from its low and in Q2 2026 stood 11.7% above the 2008 peak in nominal terms2. Even so, central Athens is still one of the cheapest large European cities per square metre, at about €3,442/m² against a 28-city European average of €9,090/m²4. New supply is still far below need. Dwellings in new residential building permits ranged between only 5,500 and 41,700 a year in 2012–202528. For scale, the census records about 91.5k dwellings a year actually built in 2001–201029 (a different measure, see section 2.9). This study's model puts the accumulated housing gap at about 140.9k–489.7k dwellings. Under plausible scenarios that gap needs about 10–28 years to close. At today's build rate, in the central case, it does not close at all (section 2.9).
The investment: our own conversion project.
We buy a commercial building, convert it to apartments under a fixed-price contract and sell the units off-plan to Golden Visa buyers (each GV unit must cost at least €250,000). We model it as two matched scenarios: Average (works €1,100/m², 13 units of 58 m² at €250,000, ≈ €4,310/m²) and Premium (design-led works €1,600/m², 15 smaller units of 50 m² at €250,000, €5,000/m²). This gives us full control over price, design, cost and schedule, with the execution and regulatory risk that comes with it.
Matched by design. An earlier draft built at designer cost and sold at an average price. That mismatch is avoided here: each scenario pairs a works budget with the sale price that specification can commandA11. Both scenarios are Golden Visa products, and every unit is priced at exactly €250,000. Premium reaches that price with a higher €/m² on smaller units (15 × 50 m² instead of 13 × 58 m²).
Recommended start. One pilot conversion project, held in its own Greek company (IKE), but only on a building and contract that meet the go/no-go conditions below. The Average specification is the more robust default; Premium is worth choosing only where the building and location clearly support €5,000/m² or more. Expand only after the pilot is delivered.
Indicative capital. About €1.7m for the pilot: €1.40m (Average) to €1.44m (Premium) peak equity (€1.40m–€1.45m across the base cases and the two stress tests) plus a €0.30m reserve.
Indicative returns (worked example: Metaxourgeio, Athens, 840 m²; Average 13 apartments, Premium 15 apartments). All figures are after 22% Greek corporate tax and 5% dividend withholding:
| Average | Premium | |
|---|---|---|
| Units | 13 × 58 m² | 15 × 50 m² |
| Works (excl. VAT) / sale price | €1,100/m² / €250,000 (≈ €4,310/m²) | €1,600/m² / €250,000 (€5,000/m²) |
| Total development cost | €2,779,633 | €3,369,604 |
| Sales revenue | €3,250,000 | €3,750,000 |
| Profit before tax (on cost) | €470,367 (16.9%) | €380,396 (11.3%) |
| Net profit to investors | €348,542 | €281,874 |
| Peak equity | €1,403,410 | €1,437,385 |
| ROI on equity / equity IRR (p.a.) | 24.8% / 23.8% | 19.6% / 17.1% |
| Duration | 24 months | 24 months |
| Stress: works cost +10%, on its own (net) | €249,670 | €140,248 |
| Stress: 6-month delay, on its own (net) | €339,650 | €272,982 |
| If the 12% contingency is not needed: profit before tax / net / ROI / IRR | €600,269 / €444,800 / 31.7% / 29.5% | €566,470 / €419,755 / 29.2% / 24.6% |
| Upside (not in base): ~210 m² building rights, if unlocked (net) | €673,073 (+3 units) | €641,193 (+4 units) |
| Hold 100% and rent: gross ROI | 5.4% at €16/m² | 5.5% at €20/m² |
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
Hold and rent instead of selling (section 7.4). Keeping all units (13 Average, 15 Premium) on long-term leases gives a gross ROI of about 5.4% a year for Average (rent €16/m²; €144,768 ÷ €2,699,197) and 5.5% for Premium (rent €20/m²; €180,000 ÷ €3,279,104), about 3.7% and 4.0% net before tax. Selling clearly beats holding in both scenarios; holding is a fallback, not the plan.
Contingency is not lost money. The base case is conservative: the full 12% contingency (€129,902 Average, €186,074 Premium) is paid in by investors and treated as spent. If the works stay within budget, the unspent contingency is released back to the IKE at the end and counted as profit. Profit before tax rises by the full amount, to €600,269 (Average) and €566,470 (Premium). After 22% corporate tax and 5% dividend withholding, net profit rises to €444,800 and €419,755, on the same committed equity (section 7.3).
Upside not in the base case: ~210 m² of unused building rights. If the rights are legally confirmed and the structure can carry them, they add 3 Average units or 4 Premium units, about +€324,531 and +€359,319 net, but only if the extra units can also be sold at €250,000 to Golden Visa buyers. That is not confirmed for a commercial building: the published rules extend the €250,000 route to rooftop additions only for industrial and listed buildings (section 7.3). Weighted by an illustrative 50% chance, the upside is worth about €162,266 and €179,660.
Verdict
VERDICT: both matched scenarios are viable at their base inputs; Average is the more robust. Average makes 16.9% on cost before tax (€348,542 net, 23.8% IRR), Premium 11.3% (€281,874 net, 17.1% IRR). Average has more headroom (sale price can fall 14.8% before a loss, against 10.4% for Premium), and both stay profitable in each of the two stress tests run on its own (works cost +10%: €249,670 against €140,248; 6-month delay: €339,650 against €272,982). Premium earns more than Average only if it sells above its €5,000/m² base (€390,801 net at €5,200/m², i.e. €260,000 per 50 m² unit). Honest flags: every unit in both scenarios is priced exactly on the €250,000 Golden Visa floor, so neither has a price buffer: any discount takes a unit out of the Golden Visa. Average's €4,310/m² is above the Spitogatos new-build average of about €4,000/m²45. Premium's 15 units of 50 m² use 750 of the 755 m² above ground and need a layout check by the architect; the works budget per m² is kept unchanged, although two more kitchens and bathrooms may cost more. Premium's €5,000/m² is in the upper part of today's evidence and must be earned by the product. We recommend going ahead only if the building is bought at or below the €1.2m asking price (breakeven purchase price €1,637,000 Average, €1,554,000 Premium; a 20% margin would need ≤ €1,133,000 for Average and ≤ €971,000 for Premium) and the works are fixed-price within the chosen scenario's budget.
Source: This study's financial model
Section 02
The Greek real estate market: why it is an opportunity
2.1 From crash to recovery
Greek apartment prices peaked in Q3 2008 (index 102.2, 2007 = 100) and fell for nine years to Q3 2017 (58.9), a fall of −42.4%2. Recovery began in 2018 and gathered pace: +7.2% in 2019, +11.9% in 2022, +13.9% in 2023, +9.1% in 2024 and +8.3% in 20251,2. In Q2 2026 prices were still rising, by +5.5% year on year nationally and +5.0% in Athens. Price growth is clearly slowing1.
Note on the figures: the annual percentage changes are the official Bank of Greece rates, which the Bank computes from unrounded data. Recomputing them from the rounded index levels in the chart can give a difference of ±0.1 percentage point (for example 2022 and 2023).
Honest note: in real (inflation-adjusted) terms prices are still below their 2008 level. The fast gains of 2022–23 are not expected to repeat. The Bank of Greece describes the outlook as "cautiously positive"12.
- Peak 102.2 (Q3 2008)
- Trough 58.9 (Q3 2017): −42.4%
- +93.9% from trough; 11.7% above the 2008 peak (nominal)
Source: Bank of Greece, Index of apartment prices by age, data to Q2 20261,2
Latest (Q2 2026): Athens +5.0% · Greece +5.5% year on year. Units: % year on year (2025 and 2026 provisional).
Source: Bank of Greece indices by geographical area and by age1,2, Athens series as compiled by GreekProps3
2.2 Athens is still cheap compared with other European cities
Source: Deutsche Bank Research, Mapping the World's Prices 2026, via Euronews, 30 Aug 20264. Athens is 62.1% below the 28-city average. Local portal data agree: homes up to 80 m² in the xe.gr "Athens" area had an average asking price of €3,087/m² in Q3 2026 (+10.2% y/y)3.
Athens €3,442/m² vs 28-city European average €9,090/m² (−62.1%)
Source: Deutsche Bank Research Institute, Mapping the World's Prices 2026, via Euronews, 30 Aug 20264
2.3 A stronger economy
- Investment grade regained in 2023: Scope (Aug), DBRS (Sep), S&P (20 Oct) and Fitch (Dec 2023); Moody's followed on 14 Mar 20257,8,9.
- Growth above the euro area: real GDP +2.0% (2023), +2.1% (2024), +2.1% (2025), against +0.4%, +1.3% and +1.2% for the euro area5.
- Debt falling fast: from 209.4% of GDP (2020) to 145.4% (2025). It is still high, but it is the fastest reduction in the EU6.
Units: % change.
Source: Eurostat tec00115, updated 21 Oct 20265
Source: Eurostat teina225, updated 21 Oct 20266
2.4 Record tourism
- 2025: 43.3 million inbound visitors (including 5.3m cruise passengers) and €23.6 bn travel receipts (+9.4%), both records10,11.
- Excluding cruise: 38.0m arrivals and €22.6bn receipts, against 31.3m and €17.7bn in 201911.
Arrivals (million)
Travel receipts (€ bn)
2025 including cruise: 43.3 million visitors and €23.6 bn receipts (+9.4%)
Source: INSETE Intelligence, Inbound Tourism to Greece 2025 (June 2026)11; Bank of Greece10
2.5 Foreign demand
- Net foreign direct investment in Greek real estate (Bank of Greece data; 2019–2022 as reported by the Greek press) rose from €1,449m in 201913 to a record €2,750.3m in 2024 (+28.9%)15,12, then fell to €2,055.6m in 2025 (−25.3%)12. The pandemic year 2020 saw €874.9m14; 2021 €1,176m and 2022 €1,975m13.
- Golden Visa applications: 8,426 (2023)15 and 9,387 (2024), then 7,031 in 2025 (−25.1%) after the thresholds were raised12. The 2024 figure is the revised figure in the Bank of Greece Annual Report 2025.
Honest note: foreign demand is still large but has cooled since the 2024 rule changes. Our model does not assume that it returns to its 2024 peak.
2023 is derived from the Bank of Greece's +28.9% growth rate for 2024. 2020 fell because of the pandemic. 2025 fell by 25.3% after the higher Golden Visa thresholds.
Source: Bank of Greece data. 2019–2022 from secondary press sources citing Bank of Greece data: 2019, 2021, 2022 via in.gr/ot.gr13; 2020 via ot.gr and eKathimerini14. 2024 growth from the Bank of Greece15; 2024–2025 Bank of Greece Annual Report 2025 via Naftemporiki12
2025: −25.1% after the thresholds were raised (Law 5100/2024).
Source: Bank of Greece Governor's Report 2024 (2023 figure)15; Bank of Greece Annual Report 2025 (2024 and 2025)12
2.6 Large projects reshaping Athens
- The Ellinikon (former airport, southern coast) is one of Europe's largest urban regeneration projects. It is now in its delivery phase, with about €1.27bn of cumulative capex in buildings and infrastructure16. Greece's first skyscraper, the 200 m Riviera Tower, has reached full height17. All 315 coastal-front homes are sold16.
- Metro Line 4 (section A, Alsos Veikou–Goudi): 12.8 km and 15 underground stations19. Completion has slipped to 203218, so it will not help a 2027–29 pilot.
- Piraeus: a record of about 1.85 million cruise passengers in 202520. Container throughput at the COSCO terminal fell about 6% to 3.98m TEU20.
2.7 The Golden Visa: why conversions are the accessible entry
| Route | Minimum investment | Where | Key conditions |
|---|---|---|---|
| Standard – high-demand areas | €800,000 | Attica (incl. Athens & Piraeus), Thessaloniki regional unit, Mykonos, Santorini, islands >3,100 residents | Single property; ≥120 m² main areas; no short-term letting |
| Standard – rest of Greece | €400,000 | All other areas | Single property; ≥120 m² main areas; no short-term letting |
| Conversion to residential | €250,000 | Nationwide | Change of use legally completed after 5 Apr 2024 and before the application; no minimum size; the €250k benefit can be used only once per property |
| Listed-building restoration | €250,000 | Nationwide | Excluded from this venture by policy |
Source: Law 5100/202421; Circular 1/21.04.2026 per EY22; IBA, 9 Sep 202623
Since Law 5100/2024, a standard Golden Visa in Attica (including Athens and Piraeus), Thessaloniki, Mykonos, Santorini and islands with more than 3,100 residents needs €800,000 for a single property of at least 120 m². Elsewhere the minimum is €400,00021,23. The €250,000 threshold survives for properties converted from non-residential to residential use. No minimum size applies, but the change of use must be legally completed after 5 Apr 2024 and before the buyer applies21,22,24. As a result, converted units in central Athens are the only way into the Athens Golden Visa market at about a third of the standard price. This is the niche our conversion project targets.
Important rules:
- The €250k benefit applies to a converted property only once. A later buyer of the same unit cannot use the €250k route again22.
- GV properties cannot be let short-term (Airbnb-type platforms). Long-term letting is allowed22,23.
- Listed-building restoration is a second €250k route. We exclude it by policy (see section 4).
2.8 What could change (read this box carefully)
What could change
- Higher transfer tax for non-EU buyers (draft law). A bill was put to public consultation on 18 Oct 2026 (comments close 1 Nov 2026). It would raise the transfer tax on homes bought by natural persons who are tax-resident outside the EU/EEA from 3.09% to 15.45% (15% plus the 3% municipal surcharge). The new rate would apply to final contracts signed from 1 July 202725,26. The government aims to pass it in November 2026, and Parliament can still change it. The test is tax residence, not nationality. The draft refers to natural persons, not companies26. On a €250,000 unit (the unit price in both our scenarios) the buyer's tax would rise from €7,725 to €38,625 (+€30,900). Impact on us: the tax would apply to every non-EU-tax-resident buyer in the market, not only to our units, so market prices are expected to adjust. It is therefore not modelled as a cost absorbed by the project (section 8).
- Golden Visa politics. The rules were tightened in 2023 and again in 2024. On 15 Oct 2026 the migration minister said permits obtained through disguised discounts, or properties sublet short-term, would be revoked (no legal text yet)27. A future government could narrow or close the €250k conversion route.
- VAT suspension on new buildings. The 24% VAT on new-build sales has been suspended. The same draft bill extends the suspension for 202725, so VAT could return from 2028. Our conversion units are assumed to fall under transfer tax, not VATA4.
- Building-code incentives. In 2025 the Council of State (plenary decisions 146–149/2025) ruled the New Building Code bonus incentives for extra floor area and height unconstitutional. Law 5197/2025 protects only projects legally started by 11 Dec 202415,49. Any "extra building rights" on a building must be legally confirmed, not assumed.
- Possible positives. The National Housing Strategy 2026–2035 proposes a Golden Visa "portfolio" route tied to long-term letting. It is not yet law23.
2.9 The supply gap: how long will strong demand for new housing last?
The facts
- Building collapsed. Dwellings in new residential building permits fell from 174,400 (2005) to 5,500 (2015). They recovered only to 41,700 (2024) and 31,900 (2025)28. The census shows 915,138 dwellings built in 2001–2010 (about 91.5k a year) but only 173,624 in 2011–202129.
- Two different measures: permits (Eurostat) count dwellings authorised in a year; the census counts dwellings standing in 2021 by the period in which they were built. They are shown together for scale only. All gap calculations below use the Eurostat permit series (2005–2025), lagged two years.
- The stock is old. 51.3% of Greece's 6,596,761 dwellings (and 53.5% in Attica) were built before 1981. Only 2.6% (Attica 2.2%) were built in 2011–202129. (8 dwellings nationally and 6 in Attica are not allocated to a period.)
- Independent estimates agree there is a gap. Piraeus Bank estimates a shortage of about 212,000 dwellings built up in 2012–2021 alone30. NBG estimated excess demand of about 30,000 dwellings a year in 2023–2431. Both use their own estimates of construction, not the Eurostat series, so they are independent cross-checks rather than inputs. The IMF notes labour and capacity constraints that limit how fast building can grow32.
- Honest counterpoint: the 2021 census also counted 2.28 million unoccupied dwellings (34.5%; Attica 24.3%)29. Many are holiday homes, village houses or buildings in poor condition. Some can return to the market, so our model includes a "vacant-home reactivation" scenario.
The model (transparent; all calculations in this study's financial model)
Step 1 – completions. Completions in year t are taken as dwellings permitted in year t−2A1. This proxy matches the census well: 178.1k permitted in 2009–2019 against 173.6k actually built in 2011–2021 (ratio 0.97). Completions 2010–2025 total 335.9k.
Step 2 – annual need = household formation + replacement of obsolete stock + non-resident / second-home / short-term-rental demandA2:
| Component | Low | Central | High | Basis |
|---|---|---|---|---|
| New households / yr | 15.0k | 19.7k | 20.0k | +197k households 2011–202130 |
| Replacement (share of 4,319,146 occupied dwellings) | 0.25% = 10.8k | 0.35% = 15.1k | 0.50% = 21.6k | assumption; old stock29 |
| Non-resident, 2nd home, STR | 4.0k | 7.0k | 10.0k | assumption; strong short-term-rental growth in 2011–2130, now slowed by STR freezes and GV changes |
| Total need / yr | 29.8k | 41.8k | 51.6k |
Step 3 – formula. Cumulative shortfall (2010–2025) = Σ (annual need − completions) = 16 × need − 335.9k
| Low | Central | High | |
|---|---|---|---|
| Cumulative shortfall 2010–2025 | 140.9k | 332.9k | 489.7k |
The central estimate is consistent with Piraeus Bank's 212k for 2012–2021 alone30.
Step 4 – years to close the gap. Year by year from 1 Jan 2026: shortfall + need − completions − vacant reactivation. Completions in 2026 and 2027 are fixed by the permits already issued in 2024 and 2025 (41.7k and 31.9k); the scenario build rate applies from 2028. The same calculation drives the projection chart.
| Need | Build rate from 2028 | Years to close (closing year): no reactivation / +5k a year vacant reactivation |
|---|---|---|
| Low | 55k/yr | 7.0 (2033) / 5.9 (2031) |
| Low | 45k/yr | 10.3 (2036) / 7.8 (2033) |
| Low | 34.7k/yr (current) | 27.9 (2053) / 13.8 (2039) |
| Central | 55k/yr | 28.0 (2053) / 20.3 (2046) |
| Central | 45k/yr | never / 42.6 (2068) |
| Central | 34.7k/yr (current) | never / never: the gap keeps growing |
| High | any rate up to 55k/yr | never |
Result
Under plausible scenarios, the housing gap takes about 10–28 years to close (the 10.3-year end assumes low need and a higher building recovery without reactivation; the 28.0-year end assumes central need and a strong recovery without reactivation). Grid cells below 10 years are shown in the table but are not used for the headline: a national build-out that closes the gap faster is not considered realisticA2. At today's build rate (~35k a year) the central-case gap does not close at all.
What this means for investors: our pilot lasts about 24 months. Even in the most optimistic case, the shortage outlasts it. However, a national housing shortage does not by itself guarantee demand for €250k Golden Visa units, which depends mainly on foreign buyers and the GV rules (section 12).
Bars = dwellings in building permits (Eurostat). The reference line = dwellings actually built per the 2021 census. These are different measures and are shown together only for scale. Dwelling counts for 2000–2004 are not in the harmonised Eurostat series.
Source: Eurostat sts_cobp_a, updated 21 Oct 202628; Eurostat cens_21dwop_r329
- Before 1919128,787
- 1919–1945268,775
- 1946–1960627,713
- 1961–19802,356,334
- 1981–20002,126,382
- 2001–2010915,138
- 2011–2015112,758
- 2016–202160,866
- Period not allocated8
51.3% built before 1981 · only 2.6% built 2011–2021 (Attica: 53.5% / 2.2%)
Total 6,596,761 dwellings; 8 are not allocated to a period in the Eurostat table.
Source: Eurostat cens_21dwop_r3 (ELSTAT Census 2021)29
Source: This study's financial model; Eurostat28
Units: thousand dwellings. Cross-check: Piraeus Bank estimates about 212k for 2012–2021, using its own construction estimates rather than the Eurostat permit series [S30].
Units: thousand dwellings (shortfall still to be closed).
Source: This study's financial model
| Annual need · vacant-home reactivation | Current (34.7k) | Higher (45.0k) | Strong (55.0k) |
|---|---|---|---|
| Low (29.8k)no vacant-home reactivation | 27.9(2053) | 10.3(2036) | 7.0(2033) |
| Low (29.8k)+5k/yr vacant homes reactivated | 13.8(2039) | 7.8(2033) | 5.9(2031) |
| Central (41.8k)no vacant-home reactivation | never at this rate | never at this rate | 28.0(2053) |
| Central (41.8k)+5k/yr vacant homes reactivated | never at this rate | 42.6(2068) | 20.3(2046) |
| High (51.6k)no vacant-home reactivation | never at this rate | never at this rate | never at this rate |
| High (51.6k)+5k/yr vacant homes reactivated | never at this rate | never at this rate | never at this rate |
Columns: future completions per year from 2028. Cells: years to close the gap (year in which it closes). Counted from 1 Jan 2026. Headline range uses only plausible cells of at least 10 years [A2]; faster cells are shown but treated as unrealistic.
Source: This study's financial model
Section 03
The partnership model
Investors/partners provide the capital. Funds go in as equity into a dedicated Greek company (IKE) for each project.
Paschalis Filios provides:
- Local market knowledge and project selection. He screens buildings, negotiates prices and filters out weak deals early.
- Coordination of an independent professional team: partner civil engineers and architects, lawyers, and a chartered auditor.
- Construction oversight. He supervises builders against the fixed-price contract, schedule and quality standard.
- Sales. His company will handle sales of the finished units.
- Reporting. Investors receive regular progress and cost reports, with audited accounts per IKE.
Experience
- Has worked with investors in Dubai, Thailand and Greece.
- 2004–2011: builder/developer in Crete, building holiday homes and selling them to foreign investors. This gives him hands-on construction experience: he knows what works cost, where projects overrun, and how to control builders and quality on site.
- Greek real estate professional.
“Investors bring the capital. I bring local knowledge, a professional team and builder's discipline on site.”– Paschalis Filios
Section 04
The investment: our own conversion project
- How it works:
- Full due diligence on a commercial building (section 11).
- Purchase through the project IKE.
- Change-of-use and building permits.
- A fixed-price contract with a builder/developer to convert the building to apartments.
- Legal completion of the change of use.
- Off-plan sale of the units from permit issue (10% deposit, 10% at the preliminary agreement, 40% during works, 40% at the final contractA10); GV units at €250,000 or more.
- Pros: full control over price, design, cost and schedule; the highest upside if purchase price and works cost are right; a clear legal niche (GV €250k); the national shortage of modern small apartments supports a fallback local market.
- Cons: highest execution risk (permits, structure, cost overruns, delays); regulatory risk (GV rules, the 2027 transfer tax for non-EU buyers); capital is locked in for about 24 months; little liquidity before completion; the margin is sensitive to cost overruns (works +10% on its own: Average €249,670 net, Premium €140,248).
- Indicative margin (model): Average 16.9%, Premium 11.3% profit on cost in the base case; with works +10% on its own, 11.6% and 5.3%. Risk: high. Capital (peak equity): €1.40m (Average) to €1.44m (Premium) per project. Timeline: 24 months base in both scenarios (30 with a 6-month delay).
What we exclude, and why
- Buying and renovating old residential apartments: they do not qualify for the €250k Golden Visa in Athens, and the market is crowded with small investors, so margins are low and uncertain.
- Listed or preserved buildings: never. Approvals are slow and unpredictable, costs are very high, and the law adds strict obligations: no sale before restoration, a €150,000 fine and revocation of the permit if restoration fails23. We will only buy buildings that are confirmed in due diligence to be non-listed.
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
Section 05
Recommendation
- Start with one pilot conversion project. Choose a whole commercial building in central Athens or Piraeus, with a peak equity need of about €1.40m–€1.44m.
- Choose the specification before buying, and keep cost and price matchedA11. Default to Average (works ≤ €1,100/m² excl. VAT, units at €250,000). Choose Premium (works ≤ €1,600/m², 15 units of 50 m² at €250,000) only if comparable design-led GV units in the area are selling at €5,000/m² or more. Never combine the Premium budget with Average prices.
- Set clear go/no-go conditions before signing: for a building like the worked example, purchase price ≤ about €1.2m (breakeven purchase price €1,637,000 Average, €1,554,000 Premium); a fixed-price conversion contract within the scenario's budget (breakeven works €1,508/m² Average, €1,930/m² Premium); a credible off-plan price list at ≥ €250,000 per unit; due diligence passed; and a clear view of the final 2027 transfer-tax law.
- Expand after delivery: use the pilot's audited results to decide on project 2.
Units: € million.
Source: This study's financial model
One pilot conversion project: €1.40m–€1.44m peak equity + €0.30m reserve, about €1.7m in total. A second project is considered only after the pilot is delivered.
Section 06
Indicative buildings currently on the market
Indicative asking prices, subject to due diligence. These are not offers, and availability may change.
| # | Area | Size (m²) | Indicative asking price | €/m² | Key note |
|---|---|---|---|---|---|
| 1 | Athens – Metaxourgeio | 840 (incl. 85 m² basement) | €1,200,000 | 1,429 | Existing architectural study for 13 apartments (40–70 m²); about 210 m² of unused building rights (to be legally confirmed); the same building is offered at €1.2–1.35m, so the price is negotiable |
| 2 | Piraeus | 744 (incl. 144 m² not yet built) | €900,000 | 1,210 | Study and permit supervision for 10–12 apartments (about 60 m²) included in the price; 1993 frame; exact location to be confirmed |
| 3 | Piraeus – Kastella | 1,138 | €1,050,000 | 923 | Advertised as in a residential zone; energy class B; only 4 deep levels (about 280 m² each), so natural light must be checked |
| 4 | Kallithea – Evangelistria | 1,250 | €1,300,000 | 1,040 | 5 floors plus mezzanine; two basements reduce the usable area; near Kallithea/Tavros rail stations |
| 5 | Athens – Pl. Attikis | 860 | €1,380,000 | 1,605 | 8 floors (built 1982); metro about 300 m away; advertised as suitable for change of use |
Indicative asking prices, subject to due diligence. Not offers; availability may change.
Source: Internal screening of Greek property portals, October 202642
Source: internal screening of whole commercial buildings on Greek property portals, October 202642.
Highlighted: the building used in the worked example (section 7). Units: €/m² (asking).
Source: 42
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
Section 07
Worked example: Metaxourgeio, 840 m², 13 or 15 apartments (indicative)
7.1 Key assumptions (both scenarios)
- Purchase: €1,200,000 (lowest asking price) + transfer tax 3.09% + about 2% notary, lawyer and land registry costs + 2% buyer's broker commission plus 24% VAT (€29,760)A6,52, + €25,000 due diligence. Same in both scenarios.
- Units (sized so every unit is exactly €250,000): Average 13 apartments of about 58 m² gross (755 m² above ground ÷ 13); Premium 15 apartments of 50 m² gross (€250,000 ÷ €5,000/m² = 50 m²; 750 of the 755 m² used, 5 m² slack)A5. The 85 m² basement becomes storage and technical rooms in both.
- Two matched scenariosA11: each scenario pairs a works budget with the sale price that specification can command, so we never build at designer cost and sell at an average price.
- - Average: works €1,100/m² above ground, inside the €700–1,200/m² full-renovation band quoted by Athens architects33A3; 13 × 58 m² units at €250,000 (≈ €4,310/m²)A5; rent €16/m²/monthA8.
- - Premium: design-led works €1,600/m², inside a €1,400–1,800/m² design-led band (Athens architects quote €1,200–1,600+/m² for design-led work33)A3; 15 × 50 m² units at €250,000 (€5,000/m²; sensitivity €5,200–5,500/m², i.e. €260,000–€275,000 per unit)A5; rent €20/m²/monthA8.
- - Basement €500/m² in both. All works costs excl. VAT.
- VAT 24% on works is treated as a cost (non-recoverable)A4. Because contingency (12%) and project management (4%) are calculated on works including VAT, the full VAT impact is €243,043 of extra cost for Average and €348,139 for Premium (€180,095 and €257,970 less net profit). If a tax adviser confirmed that all of it could be recovered, net profit would be €528,637 (Average) and €539,844 (Premium). This is not assumed.
- Studies and permits 9% of works excl. VAT; contingency 12% and project management and independent site supervision 4%, both of works incl. VAT. The contingency is paid in and treated as spent in the base case; any unused part returns to profitA12.
- Sales: sold off-plan from permit issue (month 6) on a Dubai-style payment planA10: 10% deposit (month 6), 10% at the preliminary agreement (month 7), 40% in equal monthly instalments during works (months 6–17), and 40% at completion and final contracts (months 21–22). Collected before completion: €1,950,000 (Average), €2,250,000 (Premium). Marketing and sales costs 2% of revenue, spread over months 6–22; €1,500 per unit for certificates and sale documents at the final contracts.
- Company costs: IKE accounting, audit, legal and bank €1,000/month for the whole 24 months; ENFIA, insurance and utilities €1,000/month from acquisition (month 3) to the end (21 months)A6.
- Tax: Greek corporate tax 22% on profit; 5% withholding on dividends35. Funded 100% by equity, with no bank debt.
- Timeline (both scenarios): due diligence months 0–3 → permits 3–6 → works 6–18 → completion and legal change of use 18–20 → final sale contracts months 21–22 → tax and distribution month 24: 24 months in total, the owner's maximum cycleA5. Off-plan sales run from month 6.
7.2 Are €4,310 and €5,000/m² realistic for 58 m² and 50 m² units? (honest check)
- Average = the Golden Visa floor, not the market average. The €250,000 Golden Visa floor needs €4,310/m² at 58 m². Because the owner requires every unit to be GV-eligible, the Average scenario is priced exactly at €250,000, not at the Spitogatos Athens Centre new-build average of about €4,000/m²45 (which would give about €232,000 per unit, below the floor). So "Average" describes the specification, while its price is about 7.7% above the new-build average, with no buffer: any discount below €250,000 takes the unit out of the Golden Visa, and disguised discounts are being targeted27.
- Premium at €5,000/m² (€250,000 for 50 m²) is also exactly on the €250,000 floor, with no price buffer either. Its €/m² is above the Spitogatos new-build average45, above the Deloitte / Prodexpo Athens new-build figure of about €4,360/m²46 and the xe.gr new-build median asking price of about €4,407/m² (accessed 28 Oct 2026)47. It sits in the upper part of an operating Golden Visa conversion project in Metaxourgeio, which is asking €3,776–5,198/m², including a 57.3 m² unit at €250,000 (€4,363/m²)34. The €5,200–5,500/m² sensitivity is at or just above that project's highest unit.
- The ordinary local market of old, unrenovated properties (not renovated or new-build stock) is much lower: xe.gr Athens average €3,087/m² (≤80 m², Q3 2026) and Spitogatos Athens-centre average €2,439/m² (Q3 2025)3.
Conclusion: both prices depend on Golden Visa buyers. Average needs only a genuine new-build finish to reach €250,000. Premium needs a clearly design-led product and location to reach €5,000/m² on smaller units; the evidence for that price is thinner. Neither has room for discounts. The units are not priced against the old, unrenovated stock: if Golden Visa demand weakens, the fallback is to hold and let the units (section 7.4) until they can be sold at renovated / new-build prices.
Both scenarios are Golden Visa products: every unit is priced at exactly €250,000, the GV floor. Average reaches it with 13 × 58 m² units (€4,310/m²), above the Spitogatos new-build average of about €4,000/m², with no price buffer. Premium reaches it with smaller 15 × 50 m² units at €5,000/m², which sits in the upper part of the Metaxourgeio GV project's €3,776–5,198/m² range and needs a genuinely design-led product.
Source: GreekProps (Spitogatos, xe.gr)3; Metaxourgeio GV project34; Spitogatos Insights45; Deloitte/Prodexpo46; xe.gr47; owner pricesA5
7.3 Indicative P&L (both scenarios, from this study's financial model)
| Line | Average (€) | Premium (€) |
|---|---|---|
| Acquisition price | 1,200,000 | 1,200,000 |
| Transfer tax 3.09% | 37,080 | 37,080 |
| Notary, lawyer, land registry (~2%) | 24,000 | 24,000 |
| Acquisition broker commission (2% of purchase price + 24% VAT) | 29,760 | 29,760 |
| Due diligence (engineers, lawyers, auditor) | 25,000 | 25,000 |
| Studies & permits (9% of works excl. VAT) | 78,570 | 112,545 |
| Conversion construction (excl. VAT) | 873,000 | 1,250,500 |
| Non-recoverable VAT 24% on construction | 209,520 | 300,120 |
| Contingency (12% of works incl. VAT) | 129,902 | 186,074 |
| Project management & site supervision (4% of works incl. VAT) | 43,301 | 62,025 |
| Marketing & sales costs (2% of revenue) | 65,000 | 75,000 |
| Unit sale documents & certificates | 19,500 | 22,500 |
| IKE running costs (24 months × €1,000) | 24,000 | 24,000 |
| Holding costs: ENFIA, insurance, utilities (21 months from acquisition × €1,000) | 21,000 | 21,000 |
| Total development cost | 2,779,633 (≈ €213,818 per unit) | 3,369,604 (≈ €224,640 per unit) |
| Sales revenue (GDV) | 3,250,000 (13 × €250,000) | 3,750,000 (15 × €250,000) |
| Profit before tax | 470,367 (16.9% on cost, 14.5% on revenue) | 380,396 (11.3% on cost, 10.1% on revenue) |
| Corporate tax 22% | −103,481 | −83,687 |
| Profit after tax | 366,886 | 296,709 |
| Dividend withholding tax 5% | −18,344 | −14,835 |
| Net profit to investors | 348,542 | 281,874 |
| Peak equity required | 1,403,410 (month 5) | 1,437,385 (month 5) |
| ROI on equity (whole project) | 24.8% | 19.6% |
| Equity IRR (annualised, after tax) | 23.8% | 17.1% |
| Duration | 24 months | 24 months |
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
The cash-flow chart and this table come from the same monthly calculation: the final cumulative cash position in month 24 equals the net profit, and the lowest point equals the peak equity. Because buyers pay 60% of the price during constructionA10, the equity peak comes at month 5, just before off-plan collections start; without off-plan sales the peak equity would be €2,689,133 (Average) and €3,266,104 (Premium).
Premium spends €589,971 more to earn €500,000 more revenue (two more units of €250,000), so at its €5,000/m² base it makes €66,668 less net profit than Average on slightly more equity.
Average: €348,542 net profit on €1,403,410 equity · 24.8% ROI · 23.8% IRR. Premium: €281,874 on €1,437,385 · 19.6% ROI · 17.1% IRR. Both over 24 months.
An earlier internal estimate for a larger generic project (about €3.19m cost, €5.25m GDV, about €1.14m net) does not apply to this building. The figures above were recomputed from scratch.
Contingency: budgeted and paid in, but returned as profit if it is not neededA12. The base case above treats the full 12% contingency as spent: €129,902 (Average) and €186,074 (Premium). Investors still commit this money, because overruns are common, but it is a reserve, not a sunk cost. Whatever is not spent was never a real cost, so it is removed from total development cost. Profit before tax (gross) rises by the full unspent amount. Net profit rises by less, because the extra profit is taxed in the same way as the rest: 22% corporate tax, then 5% withholding on the dividend, leaving about 74 cents of each euro for investors. Peak equity is unchanged, because the contingency is paid in either way.
| Contingency outcome | Profit before tax (gross) | Net to investors | ROI / IRR |
|---|---|---|---|
| Average: fully spent (base case) | €470,367 | €348,542 | 24.8% / 23.8% |
| Average: half spent | €535,318 | €396,671 | 28.3% / 26.7% |
| Average: not needed | €600,269 (+€129,902) | €444,800 (+€96,258) | 31.7% / 29.5% |
| Premium: fully spent (base case) | €380,396 | €281,874 | 19.6% / 17.1% |
| Premium: half spent | €473,433 | €350,814 | 24.4% / 20.9% |
| Premium: not needed | €566,470 (+€186,074) | €419,755 (+€137,881) | 29.2% / 24.6% |
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
Margin on cost if the contingency is not needed: 22.7% (Average) and 17.8% (Premium), against 16.9% and 11.3% in the base case.
Upside not in the base case: ~210 m² of unused building rightsA13. The Metaxourgeio building is reported to have about 210 m² of unused building rights42. The listing does not say how this figure was calculated.
How it works. Unused building rights are the floor area the local zoning still allows on the plot (the plot's building coefficient), minus the floor area already built. They can be used by adding a floor or an extension, with a building permit under today's rules. This is not a Golden Visa or conversion benefit. In 2025 the Council of State struck down the New Building Code bonuses that let permits exceed local zoning (extra floor area and height in exchange for energy upgrades and green space), and ruled that mezzanines and the 35 m² rooftop room must now count towards floor area. Law 5197/2025 protects only projects legally started by 11 Dec 202415,49. If any part of the 210 m² relies on those bonuses, that part is gone.
The Golden Visa catch. The €250,000 route applies to property whose main spaces are converted to residential use21,24. The published rules state that rooftop additions, extensions and new buildings on the same plot qualify for the €250,000 route only for industrial buildings and listed buildings50,51. They say nothing about additions to an ordinary commercial (office or retail) building. New floor area built as residential from the start is not, on the face of the rules, a "change of use". For a commercial building, it is not confirmed that the extra units qualify for €250,000. If they do not, a Golden Visa buyer in Athens would need the standard €800,000 threshold21. The extra units would then have to be sold to ordinary buyers, at prices this study does not model.
The upside counts only if all of these prerequisites are met:
- Rights legally confirmed: a planning engineer confirms from the zoning that the ~210 m² comes from the plot's own building coefficient and height limit, not from the struck-down bonuses49. (Confirmed requirement.)
- Structure: a structural engineer confirms the 1960s frame can carry the extra floor, including any strengthening and its cost. (Our inference: standard engineering check, not a quoted rule.)
- Golden Visa eligibility of the extra units: a written opinion from Greek immigration lawyers, ideally confirmed with the Ministry of Migration and Asylum, that a rooftop addition to a commercial building being converted counts for the €250,000 route. Alternatively, confirmation that the building is legally classed as industrial. Otherwise the units do not qualify at €250,00050,51. (Not confirmed; this is the largest uncertainty.)
- Permit and timeline: the addition goes into the same building permit or revision, and the extra works fit into the 24-month cycle. (Model assumption.)
If they are met, the extra area holds 3 Average units of 58 m² (174 m²) or 4 Premium units of 50 m² (200 m²), built at the same works cost per m² as the scenario. Purchase price is unchanged.
| Average | Premium | |
|---|---|---|
| Base (no extra area) | €348,542 net · 24.8% ROI · 23.8% IRR | €281,874 net · 19.6% ROI · 17.1% IRR |
| With the upside (3 / 4 extra units) | €673,073 net · 47.4% ROI · 48.9% IRR | €641,193 net · 43.7% ROI · 40.6% IRR |
| Extra net profit if unlocked | +€324,531 | +€359,319 |
| Change in peak equity | +€17,226 | +€28,800 |
| Probability-weighted net at 25% / 50% / 75% chance | €429,675 / €510,808 / €591,940 | €371,704 / €461,534 / €551,363 |
| Extra area still breaks even up to works of | €2,747/m² | €3,186/m² |
| Upside and contingency not needed | €790,435 | €814,357 |
Indicative. All property prices, costs and projections shown here are indicative, subject to full due diligence, and may change.
The probabilities are illustrative, not an estimate. Given prerequisite 3, the lower end is the more prudent reading for a commercial building: the real chance is known only after the legal and structural checks in due diligence (section 11). Probability-weighted net = base net + chance × extra net profit. New floor area may cost more per m² than conversion; the breakeven line shows how much it could cost before the extra units stop adding profit. The upside is never used to justify the purchase price.
Off-plan collections are already in both scenarios. Their main risk is buyer protection: deposits and instalments should sit in escrow or be backed by a bank guarantee, which Greek lawyers must structureA10.
- Acquisition price€1,200,000
- Transfer tax 3.09%€37,080
- Notary, lawyer, land registry (~2%)€24,000
- Acquisition broker commission (2% of purchase price + 24% VAT)€29,760
- Due diligence (engineers, lawyers, auditor)€25,000
- Studies & permits (9% of works excl. VAT)€78,570
- Conversion construction (excl. VAT)€873,000
- Non-recoverable VAT 24% on construction€209,520
- Contingency (12% of works incl. VAT)€129,902
- Project management & site supervision (4% of works incl. VAT)€43,301
- Marketing & sales costs (2% of revenue)€65,000
- Unit sale documents & certificates€19,500
- IKE running costs (24 months × €1,000)€24,000
- Holding costs: ENFIA, insurance, utilities (21 months from acquisition × €1,000)€21,000
Source: This study's financial model
- Acquisition price€1,200,000
- Transfer tax 3.09%€37,080
- Notary, lawyer, land registry (~2%)€24,000
- Acquisition broker commission (2% of purchase price + 24% VAT)€29,760
- Due diligence (engineers, lawyers, auditor)€25,000
- Studies & permits (9% of works excl. VAT)€112,545
- Conversion construction (excl. VAT)€1,250,500
- Non-recoverable VAT 24% on construction€300,120
- Contingency (12% of works incl. VAT)€186,074
- Project management & site supervision (4% of works incl. VAT)€62,025
- Marketing & sales costs (2% of revenue)€75,000
- Unit sale documents & certificates€22,500
- IKE running costs (24 months × €1,000)€24,000
- Holding costs: ENFIA, insurance, utilities (21 months from acquisition × €1,000)€21,000
Source: This study's financial model
Bars show the running total from sales revenue down to net profit.
Source: This study's financial model
Bars show the running total from sales revenue down to net profit.
Source: This study's financial model
Peak equity: Average €1,403,410 (month 5), Premium €1,437,385 (month 5). Final position = net profit to investors: Average €348,542, Premium €281,874 (month 24)
Source: This study's financial model
7.4 Hold-and-rent alternative (both scenarios; indicative)
Instead of selling, the IKE keeps all or part of the apartments (13 in Average, 15 in Premium) and lets them on long-term residential leases. A lease for a main home runs at least 3 years by law (Law 1703/1987)43. Short-term letting is not an option here: new short-term-rental registrations are frozen in Athens districts 1–3, which include Metaxourgeio, until 31 Dec 202643.
Definition used throughout: Gross ROI = annual gross rent (all held units let at the asking rent, before vacancy, costs and tax) ÷ total development cost of the held units. No debt is assumed, so the total development cost is also the equity tied up in the held units.
Rent (matched to each specification)A8. Average €16/m²/month (€928 per unit); Premium €20/m²/month (€1,000 per unit). Cross-check: the xe.gr new-build median asking rent is about €17.23/m² (accessed 28 Oct 2026)47. All-homes averages for central Athens are much lower (about €12/m², mostly older stock)43,44. The Premium €20/m² is above the new-build median and needs a genuinely design-led product; it is an owner assumption, not market evidence. These are asking rents, not agreed rents. Other rents are shown as sensitivity.
Cost of the held units (100% hold). Start from each scenario's total cost and remove the costs that exist only because units are sold: marketing and sales costs (€65,000 Average, €75,000 Premium), unit sale documents (€19,500 and €22,500), and IKE and holding costs after completion (€8,000). There are no off-plan sales; the development period ends at completion and legal change of use (month 20). Add a letting fee of one month's rent per unitA9. Result: €2,699,197 (Average) and €3,279,104 (Premium).
Partial hold (about half sold). The sold units are sold off-plan on the same 24-month timeline; shared cost is split by number of units. Average sells 7 and holds 6: the sold units make €253,275 before tax and the held units cost €1,249,476. Premium sells 8 and holds 7: €202,878 and €1,533,982.
| Case | Rent €/m²/month | Rent per unit/month | Vacancy (net yield only) | Total cost of held units | Annual gross rent | Gross ROI | Net yield before tax | Sources |
|---|---|---|---|---|---|---|---|---|
| Average – hold 100% (13 × 58 m²), matched rent | €16.0 | €928 | 5.0% | €2,699,197 | €144,768 | 5.4% | 3.7% | A8,A9 |
| Average – sell 7 / hold 6, matched rent | €16.0 | €928 | 5.0% | €1,249,476 | €66,816 | 5.3% | 3.2% | A8,A9 |
| Average – hold 100%, rent sensitivity | €18.0 | €1,044 | 5.0% | €2,700,705 | €162,864 | 6.0% | 4.3% | A8 |
| Average – hold 100%, rent sensitivity | €20.0 | €1,160 | 5.0% | €2,702,213 | €180,960 | 6.7% | 4.8% | A8 |
| Premium – hold 100% (15 × 50 m²), matched rent | €20.0 | €1,000 | 5.0% | €3,279,104 | €180,000 | 5.5% | 4.0% | A8,A9 |
| Premium – sell 8 / hold 7, matched rent | €20.0 | €1,000 | 5.0% | €1,533,982 | €84,000 | 5.5% | 3.5% | A8,A9 |
| Premium – hold 100%, rent sensitivity | €16.0 | €800 | 5.0% | €3,276,104 | €144,000 | 4.4% | 3.0% | A8 |
| Premium – hold 100%, rent sensitivity | €18.0 | €900 | 5.0% | €3,277,604 | €162,000 | 4.9% | 3.5% | A8 |
Source: This study's financial model; owner matched rents €16/m² (Average) and €20/m² (Premium)A8, cross-checked with xe.gr new-build rents47; assumptionsA9
Net yield (sensitivity only): 5.0% vacancy, management and maintenance 10.0% of collected rent, building holding costs €12,000 a year (pro rata for the partial case) and IKE running costs €12,000 a yearA9. Before 22% corporate tax and dividend withholding tax35.
Honest read.
- Holding returns about 5.4% gross (3.7% net) for Average and 5.5% gross (4.0% net) for Premium. Selling returns 24.8% and 19.6% on equity after tax over 24 months. In both scenarios selling is clearly better; holding is a low-yield fallback.
- A unit yields 4.5% (Average) and 4.8% (Premium) gross on its sale value. That is above the 3.3–4.0% indicative gross yields reported for Athens areas (all homes)43, because we assume new-build-quality rents.
- Any case for holding rests on rent and capital growth, which this study does not model. Rents in Greece rose 5.9% in the year to September 202643; past growth does not guarantee future growth.
- Where holding can make sense: as a fallback if the Golden Visa €250k route is narrowed or closed (section 12), or for investors who want a long-term income asset in euros and accept a low yield. Long-term letting is allowed for Golden Visa property22,23, but a sitting tenant on a 3-year lease narrows the buyer pool.
Section 08
Sensitivity and stress tests
Each scenario is tested against its own base: Average against €348,542 net, Premium against €281,874 net. Two stress tests are run, each on its own and never combined: works (construction) cost +10%, and a 6-month delay. The draft 15.45% transfer tax for non-EU buyers is not treated as a project stress: it would apply to the whole market, so prices would adjust rather than the project absorbing it (section 2.8). No sale at old-stock prices is modelled: in the worst case the units are held and let (section 7.4) until they can be sold at renovated / new-build prices.
Net profit to investors (€)
Equity IRR (% p.a.)
Source: This study's financial model
| Scenario | Purchase | Works €/m² (excl. VAT) | Units × size, unit price | Duration | Total cost | Profit before tax | Net to investors | Peak equity | ROI on equity | IRR p.a. |
|---|---|---|---|---|---|---|---|---|---|---|
| Average | €1,200,000 | €1,100 | 13 × 58 m², €250,000 | 24 months | €2,779,633 | €470,367 | €348,542 | €1,403,410 | 24.8% | 23.8% |
| Premium | €1,200,000 | €1,600 | 15 × 50 m², €250,000 | 24 months | €3,369,604 | €380,396 | €281,874 | €1,437,385 | 19.6% | 17.1% |
Source: This study's financial model
Stress tests: two separate tests, each against its own base (not combined)
Note on the cost test: +10% is applied to the works (construction) budget per m²; VAT, contingency, project management and design fees calculated on the works rise with it. Purchase price, sale prices and timeline are unchanged. The test assumes the 12% contingency is also fully spent, so it is an overrun beyond the contingency.
Note on the delay test: the 6-month delay pushes completion, final contracts and distribution back by 6 months. The model adds the extra company and holding costs, so net profit falls only slightly but the IRR falls more because capital is tied up longer. Costs and sale prices are unchanged in this test; the cost increase is tested separately, not combined with the delay.
Scenario base net profit to investors: €348,542 (solid line). Bars show the change versus base; the dashed line is break-even (zero net profit). Red bars end in a loss.
Source: This study's financial model
Scenario base net profit to investors: €281,874 (solid line). Bars show the change versus base; the dashed line is break-even (zero net profit). Red bars end in a loss.
Source: This study's financial model
| Test | Average: net to investors | Average: ROI / IRR | Premium: net to investors | Premium: ROI / IRR | Months |
|---|---|---|---|---|---|
| Base (matched scenario) | €348,542 | 24.8% / 23.8% | €281,874 | 19.6% / 17.1% | 24 |
| Works (construction) cost +10%, on its own | €249,670 | 17.7% / 16.1% | €140,248 | 9.7% / 7.9% | 24 |
| 6-month delay, on its own | €339,650 | 24.1% / 16.1% | €272,982 | 18.9% / 11.9% | 30 |
Source: This study's financial model
Breakeven
- Average sale price per unit: Average breaks even at €213,080 (≈ €3,674/m², 14.8% below its price); Premium at €224,123 (≈ €4,482/m², 10.4% below its price). In both scenarios prices below €250,000 would also lose Golden Visa eligibility, so the real cushion is in cost, not price. A 20% margin on cost needs €256,853 (€4,428/m²) for Average and €270,165 (€5,403/m²) for Premium.
- Conversion cost: breakeven at about €1,508/m² for Average (budget €1,100) and €1,930/m² for Premium (budget €1,600), excl. VAT.
- Purchase price: breakeven at about €1,637,000 (Average) and €1,554,000 (Premium); a 20% profit on cost needs ≤ €1,133,000 and ≤ €971,000.
- Premium upside (units above the floor): at €5,200/m² (€260,000 per unit) Premium makes €390,801 net (27.2% ROI); at €5,500/m² (€275,000) €554,191 (38.6% ROI).
Horizontal axis: average selling price per unit.
Source: This study's financial model
Section 09
Timeline
Months from project start, base case (same in both scenarios).
Source: This study's financial model (6-month delay stress: 30 months in both scenarios)
Total: 24 months in the base case of both scenarios (the owner's maximum cycle) and 30 months in the 6-month delay test.
Section 10
Corporate and legal structure
- One Greek IKE (private company) per project. This ring-fences the risk of each project. Investors' capital goes in as share capital (equity). The IKE buys the building, signs the builder contract and sells the units.
- Greek taxation: corporate income tax of 22% on profit; 5% withholding tax on dividends35. Transfer tax on buying the building is 3.09%26. IKE accounts are kept by a Greek accountant and reviewed by a chartered auditor.
- South Africa–Greece double tax agreement: in force since 14 Feb 2003. It caps Greek dividend withholding at 5% (company holding ≥25%) or 15% (other cases). Greece's domestic rate of 5% is already at or below these caps36,35. SA-resident investors are generally taxed in South Africa on foreign dividends, with relief for Greek tax under the treaty and SA law. SA rules on controlled foreign companies may apply if SA residents together control the IKE. Each investor needs SA tax advice.
- South African exchange control: since 8 April 2026, an SA-resident adult may transfer up to R2 million a year under the Single Discretionary Allowance without a SARS AIT (TCS PIN), plus up to R10 million a year under the Foreign Investment Allowance with a SARS Approval for International Transfer (AIT). Larger amounts need SARB approval37,38. Each investor's transfers must use that investor's own allowances, through an Authorised Dealer.
- ⚠️ Regulatory caution – pooling investor money in South Africa: inviting members of the public to pool money in a scheme that is managed by others and shares in its profits may be a collective investment scheme under the Collective Investment Schemes Control Act 2002, which is regulated by the FSCA39. Soliciting SA investors for a foreign collective investment scheme requires FSCA approval under section 6540. Property syndications offered to the public carry extra disclosure duties under the Consumer Protection Act regulations41. Advisory and intermediary licensing rules may also apply. Specialist South African legal advice is required before any money is raised. Possible structures (for example, a small number of known investors each holding IKE shares directly) must be confirmed by SA counsel.
- For Golden Visa buyers: the change of use must be legally completed before they apply; their purchase must be a single property of ≥€250k21,22.
- 1South African investors (each using their own SDA R2m / FIA R10m allowances)
- 2Greek IKE – one per project (equity)
- 3Building purchase + fixed-price conversion contract
- 4Sale of units (≥€250,000, Golden Visa buyers)
- 522% Greek corporate tax
- 6Dividends (5% Greek withholding) + return of capital
- 7Investors (South African tax, with foreign tax credit – advice needed)
Section 11
Due diligence process
Team: partner civil/structural engineers and architect · Greek property lawyer · chartered auditor · tax adviser · Paschalis Filios coordinating.
Checklist (all items must be cleared before purchase):
- Title: full title search (land registry / Hellenic Cadastre), chain of ownership, seller's authority, and any co-owner or inheritance issues.
- Zoning and land use: residential use permitted in the zone; local land-use decree; building coefficient and remaining building rights (legally confirmed). Confirm the building is not listed or preserved and not in a restricted heritage zone (important in Metaxourgeio).
- Building permits and illegal works: original permit and plans match the building; any illegal or arbitrary works identified and legalised (or legalisable) at a known cost.
- Structure: survey of the 1960s–1980s frame; seismic assessment; core tests where needed; cost of any strengthening.
- Change-of-use feasibility: confirm that the architectural layout meets residential rules (light, ventilation, heights, fire escape, lift). Map the path and timetable for the change-of-use permit and the engineer's certificate that the GV buyer will need.
- Energy: current energy certificate; upgrade path to a modern class; MEP condition.
- Encumbrances: mortgages, seizures, leases (vacant possession), easements, litigation.
- Taxes and dues: ENFIA and municipal dues paid; no tax liens; tax certificates for the transfer; objective value.
- Financials: fixed-price builder offers (at least 2–3), builder references, insurance, performance guarantees; the auditor's review of the budget.
- Market check: comparable GV conversion prices and a sales plan; buyer demand after the 2027 transfer-tax law.
Section 12
Risks and mitigations
- Golden Visa €250k route narrowed or changedLikelihood: Medium · Impact: High (fallback: hold and rent until units can be sold at renovated / new-build prices)
- Draft 15.45% transfer tax for non-EU buyers from 1 Jul 2027 (market-wide)Likelihood: High (draft law) · Impact: Medium (applies to the whole market, so prices adjust; not absorbed by the project)
- Construction cost overrunLikelihood: Medium · Impact: High
- Permit / change-of-use delayLikelihood: Medium–high · Impact: Medium
- Hidden legal or technical defectsLikelihood: Low–medium (after due diligence) · Impact: High
- Slower sales / price pressureLikelihood: Medium · Impact: High
- Builder defaultLikelihood: Low · Impact: High
- South African regulation (CIS/FSCA, exchange control)Likelihood: Medium if structured wrongly · Impact: High
- EUR/ZAR currency movesLikelihood: High · Impact: Medium
Source: This study
| Risk | Impact | Mitigation |
|---|---|---|
| Golden Visa €250k route narrowed or changed | High (fallback: hold and let) | Start fast; aim to complete the change of use early; design units that also suit the long-term rental market; fallback: hold and let the units (section 7.4) until they can be sold at renovated / new-build prices, not at old-stock prices; monitor policy; keep a capital reserve |
| Draft 15.45% transfer tax for non-EU buyers from 1 Jul 2027 (market-wide) | Medium | The tax would apply to every non-EU-tax-resident buyer in the market, not only to our units, so prices are expected to adjust; it is not modelled as a cost absorbed by the project. Wait for the final law before signing; target EU/EEA-tax-resident buyers and non-EU buyers already tax-resident in the EU |
| Construction cost overrun | High (works +10% on its own: Average net €249,670, Premium €140,248) | Fixed-price contract; detailed design before tender; keep works and sale price matchedA11; 12% contingency; Paschalis's on-site oversight; staged payments against certified progress |
| Permit or change-of-use delay | Medium | Buildings with existing studies; experienced engineers; tight 3-month permit phase in the base case (start studies during due diligence); IKE costs budgeted |
| Hidden legal or technical defects | High | Full due diligence (section 11); conditional preliminary contract |
| Slower sales or price pressure | High | GV units priced at ≥ €4,310/m² (neither scenario has a price buffer); Premium only where design-led comparables support €5,000/m²; off-plan sales from month 6 with escrow-protected deposits; hold-and-rent fallback (section 7.4); no disguised discounts |
| Builder insolvency | High | Builder vetting; performance guarantee; retention; staged payments |
| Unused building rights (~210 m²) not usable | Low (upside only) | Not included in the base case; counts only after legal confirmation, structural check and GV-eligibility check (section 7.3) |
| SA regulation (CIS/FSCA, exchange control, tax) | High | SA legal and tax advice before raising capital; each investor uses own allowances |
| Currency (EUR/ZAR) | Medium | Returns are in euros; investors should consider their own currency exposure |
| Market slowdown in Greece | Medium | Prices still rising about 5% a year; breakeven price €213,080 (Average) and €224,123 (Premium), 14.8% and 10.4% below base, but neither scenario can cut below €250,000 without losing GV eligibility; short project horizon |
Section 13
Next steps
- Review of this study with interested investors and partners: open questions, goals and capital range.
- SA legal and tax advice on how investors can participate (CIS/FSCA, exchange control, tax).
- Watch the 2027 transfer-tax law (vote expected November 2026).
- Shortlist 2–3 buildings from section 6 and run a preliminary technical and legal screening.
- Full due diligence on the preferred building, with fixed-price builder offers.
- Investment decision on the pilot, then IKE set-up and acquisition.
Contact
Paschalis Filios
Investment advisory · Greece
Questions on the study, its figures or its assumptions: call or email me.
WhatsApp +30 690 884 7300 · or email paschalisfilios@gmail.com
References
Sources
All web sources were accessed on 22 October 2026 unless stated otherwise. Codes [S#] are used in the page copy and in the charts. All calculated figures come from this study's financial model. Where a figure comes from a secondary source (press or industry site), the original publisher is named.
Greek property prices and market
- Bank of Greece, Indices of residential property prices: Q2 2026, press release, 15 Sep 2026. bankofgreece.gr
- Bank of Greece, Index of apartment prices by age (quarterly and annual series, 2007 = 100, data to Q2 2026, provisional). bankofgreece.gr
- GreekProps, Athens house prices 2026: €/m² by area and index (Bank of Greece Athens index; xe.gr Q3 2026 and Spitogatos asking prices), last checked 20 Oct 2026. greekprops.com
- Deutsche Bank Research Institute, Mapping the World's Prices 2026 (Numbeo-based), as reported by Euronews, Which cities are the most expensive to buy an apartment in Europe?, 30 Aug 2026. euronews.com
Economy
- Eurostat, Real GDP growth rate – volume (tec00115), updated 21 Oct 2026. ec.europa.eu
- Eurostat, General government gross debt – annual data (teina225), updated 21 Oct 2026; and Eurostat euro indicators release of 21 Oct 2026. ec.europa.eu ; ec.europa.eu
- Reuters, S&P upgrades Greece to investment grade for first time since 2010 crisis, 20 Oct 2023. reuters.com
- European Stability Mechanism, Greece is investment grade again – why it matters to keep it (blog). esm.europa.eu
- Reuters, Moody's upgrades Greece to investment grade, 14 Mar 2025. reuters.com
Tourism and foreign demand
- Bank of Greece, press release on 2025 travel receipts and inbound travellers (final figures: 43.31 million inbound travellers incl. cruise, €23.63 bn receipts). bankofgreece.gr
- INSETE Intelligence, Inbound Tourism to Greece 2025 – special report, June 2026 (based on Bank of Greece data). insete.gr
- Naftemporiki, BoG cautiously positive on real estate market prospects (Bank of Greece Annual Report 2025: FDI in real estate €2,055.6m in 2025 vs €2,750.3m in 2024; Golden Visa applications 7,031 in 2025 vs 9,387 in 2024), 8 Apr 2026. naftemporiki.gr – The 2024 figure of 9,387 applications is the revised Bank of Greece figure and is used throughout this study.
- Secondary source citing Bank of Greece data: in.gr (source ot.gr), Real estate: 20-year record in foreign investment – €2bn inflows in 2022 (Bank of Greece data: 2019 €1,449m, used as €1,449m in this study; 2021 €1,176m; 2022 €1,975m), 18 Mar 2023. in.gr
- Secondary source citing Bank of Greece data: ot.gr, Foreign real estate investment at €875m (article in Greek) (Bank of Greece data: FDI in real estate €874.9m in 2020), 7 Apr 2021; confirmed by eKathimerini, Real estate bracing for rebound and shifts (citing Bank of Greece). ot.gr ; ekathimerini.com
- Bank of Greece, Governor's Report for 2024, Ch. IV section 3 (Apr 2025): FDI in real estate +28.9% in 2024 (used to derive the 2023 level); Golden Visa applications 8,426 in 2023; residential permits +30.3% (11M 2024); construction cost of new residential buildings +3.7%; Council of State decision 146/2025 on New Building Code incentives. (The report's preliminary 2024 Golden Visa figure was later revised; this study uses the revised 9,387 from12.) bankofgreece.gr
Major projects
- Lamda Development, The Ellinikon transitions into the delivery phase…, regulatory announcement, Euronext Athens, Sep 2026. athens.euronext.com
- Naftemporiki, Greece's first skyscraper reaches full height at 200 metres, 2026. naftemporiki.gr
- Kathimerini, Metro Line 4 "derailment" – three-year delay (infographic), 2026; and e-red, AVAX keeps €41.6M bonus as Metro Line 4 delivery set for 2032. kathimerini.gr ; ered.gr
- Elliniko Metro S.A., Line 4 Section A: Alsos Veikou – Goudi (12.8 km, 15 stations). emetro.gr
- Piraeus Port Authority (PPA S.A.), Inauguration of the 2026 cruise season – new passenger record in 2025; and Ports Europe, Piraeus Container Terminal TEU volumes fall during 2025. olp.gr ; portseurope.com
Golden Visa and Greek tax law changes
- Law 5100/2024, codified with Law 5167/2024 (Government Gazette A 49/5.4.2024), Ministry of Migration and Asylum. migration.gov.gr
- EY Greece (Platis–Anastassiadis & Associates), Law Alert: Circular 1/21.04.2026 – Golden Visa, May 2026. ey.com
- International Bar Association, The Greek Golden Visa after the 2024–2026 overhaul, 9 Sep 2026. ibanet.org
- gov.gr / Mitos, Permanent golden visa (change of use) – initial issuance. en.mitos.gov.gr
- Ministry of National Economy and Finance, Draft bill with the 90th TIF measures for 2026–2027 posted for public consultation (consultation until 1 Nov 2026; transfer-tax increase from 1 Jul 2027 for natural persons not tax-resident in the EU/EEA; VAT exemption on new buildings extended for 2027; capital-gains-tax suspension extended for 2027), 18 Oct 2026. minfin.gov.gr
- Realtopedia, Greece drafts a 15% transfer tax on homes bought by non-EU and non-EEA tax residents from 1 July 2027 (draft art. 16 and 48(8); 15% + 3% municipal surcharge = 15.45%; current 3.09%), Oct 2026. realtopedia.com
- GreekProps, Greece property week ahead: 19–25 October 2026 (status of the bill; migration minister's 15 Oct statement on revoking permits obtained through disguised discounts). greekprops.com
Housing supply
- Eurostat, Building permits – annual data (sts_cobp_a), indicator BPRM_DW "number of dwellings", residential buildings except residences for communities, Greece, updated 21 Oct 2026 (2005–2025). This is the only permit series used in the supply-gap model. ec.europa.eu
- Eurostat / ELSTAT Census 2021, Conventional dwellings by occupancy status, period of construction and NUTS 3 region (cens_21dwop_r3). Greece total 6,596,761 (8 not allocated to a period); Attica 2,162,826 (6 not allocated). ec.europa.eu
- Piraeus Bank Research, Greek Residential Real Estate: Deep and Structural Imbalances between Supply and Demand, Jan 2024 (≈212k shortfall 2012–2021; +197k households 2011–2021; strong growth of short-term-rental dwellings). Independent cross-check only: Piraeus Bank uses its own construction estimates, which are not the same as the Eurostat permit series28. piraeusgroup.gr
- National Bank of Greece, Greece Special Focus Report – housing market, 7 Sep 2023 (excess demand ~30k dwellings a year in 2023–24). Independent cross-check only, based on NBG's own estimates. nbg.gr
- IMF, Greece: 2026 Article IV Consultation – selected issues on housing (labour and capacity constraints). imf.org
Costs and prices for the worked example
- Fineline Studio (architects, Athens), How much does an apartment renovation in Athens cost? (2026: full renovation €700–1,200/m², design-led €1,200–1,600+/m², excl. VAT and design/engineering costs). finelinestudio.gr
- Developer sales presentation of an operating Golden Visa conversion project in Metaxourgeio, Athens, 2026 (asking €3,776–5,198/m²; 57.3 m² unit at €250,000 = €4,363/m²). On file; not linked.
- Internal screening of whole commercial buildings for sale in Athens/Piraeus, compiled from Greek property portals, October 2026. Not published; asking prices only.
- GreekProps, Rent in Athens 2026: asking rents by area, trends and lease rules (last verified 20 Oct 2026; accessed 28 Oct 2026). Spitogatos Q2 2026 (4 Aug 2026) average asking rent, Centre of Athens, all homes: €12/m²/month; minimum 3-year lease for a main home (Law 1703/1987, Art. 2); new short-term-rental registrations frozen in Athens districts 1–3 (incl. Metaxourgeio) until 31 Dec 2026; indicative gross yields 3.3–4.0% for Athens areas; ELSTAT rents +5.9% y/y (Sep 2026). greekprops.com
- ypodomes.com (V. Velikova), Renting a home in central Athens is an expensive business in 2026 (article in Greek, Jul 2026): average asking rent, Centre of Athens, Q2 2026 €12.3/m² (from €11.3); listed examples incl. Pl. Attikis 52 m² €9.62/m², Kypseli 54 m² €10.93/m², Votanikos 38 m² €14.74/m², Koukaki 47 m² €14.89/m². Accessed 28 Oct 2026. ypodomes.com
- Spitogatos Insights, Energy performance and year of construction: home prices for rent and sale (2025; new-builds in the Centre of Athens ~€4,000/m² asking). spitogatos.gr
- Todaygrid, Attica: new-build apartments selling at about €4,300/m² (article in Greek, citing Deloitte / Prodexpo: Athens new-build average ~€4,360/m²). todaygrid.gr
- xe.gr property portal, live listings filtered to new-builds, Athens (accessed 28 Oct 2026): median asking sale price ~€4,407/m²; median asking rent ~€17.23/m²/month. Live data, changes daily. xe.gr
- Owner judgement (Paschalis Filios, 28 Oct 2026): two matched products, both Golden Visa–eligible: Average at €250,000 per unit (the GV floor) with rent €16/m²/month, and Premium (design-led) at €5,000/m² with units resized to 50 m² so each is exactly €250,000 (15 units; sensitivity €5,200–5,500/m²), with rent €20/m²/month or more. Not a published source; seeA5,A8 andA11.
- POMIDA (Hellenic Property Federation), Law 5197/2025: changes to the New Building Code in force after the Council of State decisions, 30 May 2025, summarising Council of State plenary decisions 146–149/2025 (bonus floor area and height incentives of New Building Code Arts 10, 15(8), 19(2) and 25 unconstitutional; mezzanines and the 35 m² rooftop room now count towards floor area; protection for works started before the decision) and Law 5197/2025 (Gazette A 76/16.05.2025; continuation of works legally started by 11 Dec 2024). pomida.gr
- Ministry of Migration and Asylum, Circular 240076/Σ.9/25.09.2024 on Article 100 of Law 5038/2023 (Golden Visa): the €250,000 change-of-use route includes rooftop additions, extensions and new independent buildings on the plot for industrial buildings whose use changes to residential, and similarly for listed buildings to be restored. migration.gov.gr
- Joint Ministerial Decision 214926/2025 (Gazette B 6014/11.11.2025), documents for the €250,000 Golden Visa cases: the engineer's report certifying additions in height or extensions is provided for industrial buildings and listed buildings only. ia37rg02wpsa01.blob.core.windows.net
- Law 4072/2012, Art. 200 (brokerage fee freely negotiable, written brokerage contract required), TaxHeaven, https://www.taxheaven.gr/law/4072/2012/arthro/200 ; customary 2% plus 24% VAT per side: LEX law firm, Contracts – purchase costs, lex.gr
Tax, structure and South African rules
- PwC Worldwide Tax Summaries, Greece – Corporate – Withholding taxes (dividends 5%; treaty rate South Africa 5/15%), reviewed 8 Sep 2026; and Greece – Corporate – Taxes on corporate income (22%). taxsummaries.pwc.com ; taxsummaries.pwc.com
- SARS, Agreement between South Africa and Greece for the avoidance of double taxation (Government Gazette 24996; in force 14 Feb 2003) and SARS Dividends Tax – summary of DTA rates. sars.gov.za ; sars.gov.za
- SARS, Budget 2026 Frequently Asked Questions (Single Discretionary Allowance R2m per calendar year without TCS PIN–AIT; Foreign Investment Allowance R10m with TCS PIN–AIT). sars.gov.za
- South African Reserve Bank, Exchange Control Circular No. 6/2026 (SDA increased to R2m, effective 8 Apr 2026); summary by Exchange Control Advisory Hub, 10 Apr 2026. resbank.co.za ; exchangecontroladvisoryhub.com
- Collective Investment Schemes Control Act 45 of 2002 (South Africa). gov.za
- FSCA (then FSB), Marketing of foreign collective investment schemes – section 65 of CISCA, joint circular, 17 Mar 2003. www2.fsca.co.za
- Consumer Protection Act 68 of 2008, Regulation 15 – Public property syndication schemes. acts.co.za
Labelled assumptions (no published source; set by this study)
- A1 Completions ≈ dwellings permitted two years earlier (checked against the census: 173.6k dwellings built 2011–2021 against 178.1k permitted 2009–2019, a ratio of 0.97). Completions in 2026–2027 are fixed by the 2024–2025 permits; scenario build rates (34.7k current, 45k, 55k a year) apply from 2028.
- A2 Annual housing need components (household formation, replacement rate on 4,319,146 occupied dwellings, non-resident/second-home demand): low 29.8k, central 41.8k, high 51.6k a year. Plausible scenarios for the headline range: low need with 45k or 55k a year, and central need with 55k a year (with or without 5k a year vacant-home reactivation), and at least 10 years to close. The 10-year floor is this study's judgement: a national build-out that closes the gap in under 10 years is not considered realistic (construction capacity, labour and permitting). Cells under 10 years (5.9–7.8 years) remain in the grid but are excluded from the headline. Result: about 10–28 years (exact 10.3–28.0): low need + 45k/yr + no reactivation = 10.3 years; central need + 55k/yr + no reactivation = 28.0 years.
- A3 Conversion hard cost (owner parameter, 28 Oct 2026), matched to each scenarioA11, excl. VAT and design fees: Average €1,100/m² above ground, inside Fineline's full-renovation band of €700–1,200/m²33; Premium €1,600/m², the middle of a €1,400–1,800/m² design-led band (Fineline quotes €1,200–1,600+/m² for design-led work33). Basement €500/m² in both. Treated as a fixed-price contract target.
- A4 24% VAT on construction treated as non-recoverable (conservative; sales of units in a converted pre-2006 building are assumed to fall under transfer tax, not VAT). Contingency and project management are calculated on works including VAT, so the full VAT impact in the base case is €348,139 before tax (€286,314 net to investors). A Greek tax adviser must confirm the VAT treatment.
- A5 Sale price and unit mix (owner parameters, 28 Oct 2026), matched to each scenarioA11; both scenarios are Golden Visa–eligible and every unit is priced at exactly €250,000. Average: 13 units of ~58 m² gross ((840 − 85) ÷ 13) at €250,000 per unit (≈ €4,310/m²), exactly the €250,000 GV floor. Honesty note: this is the GV floor, not the Spitogatos Athens Centre new-build average of ~€4,000/m²45 (which would give ~€232,000, below the floor); it was set at the floor because the owner requires all units to be GV-eligible, and it leaves no price buffer. Premium: 15 units of 50 m² gross (€250,000 ÷ €5,000/m²; 750 of the 755 m² above ground used) at €250,000 per unit (€5,000/m²), sensitivity €5,200–5,500/m² (€260,000–275,000 per unit); the layout of 15 smaller units needs the architect's confirmation, and the works budget per m² is kept unchanged although two more kitchens and bathrooms may add cost; above the new-build benchmarks45,46,47 and in the upper part of the Metaxourgeio GV project range (€3,776–5,198/m²)34. Earlier bases (€4,250/m², €255,000 and €261,000 single cases; Premium at €290,000 on 58 m²) were superseded. Golden Visa caveat: any discount that takes a unit below €250,000 disqualifies it. Timeline (24 months maximum, both scenarios): due diligence months 0–3 (acquisition month 3); permits months 3–6; works months 6–18; completion and legal change of use months 18–20; final sale contracts months 21–22; corporate tax and distribution month 24.
- A6 Acquisition legal costs ~2%; buyer's broker commission 2% of the building purchase price plus 24% VAT (owner instruction, 28 Oct 2026; Greek brokerage fees are freely negotiable, customarily 2% plus 24% VAT52; €24,000 + €5,760 VAT = €29,760 at €1.2m, paid at acquisition; VAT treated as non-recoverable, like the works VATA4); studies/permits 9% of works excl. VAT; contingency 12% and project management 4% of works incl. VAT; marketing and sales costs 2% of revenue (spread over the sales window, months 6–22 in the base case); unit sale documents €1,500 per unit at the final contracts; IKE running costs (accounting, audit, legal, bank) €1,000/month over the whole project (owner parameter, raised from €500 on 28 Oct 2026 as the safer figure; 24 months = €24,000 in the base case); holding costs (ENFIA, insurance, utilities) €1,000/month from acquisition (21 months in the base case).
- A7 Stress tests (owner instruction, 28 Oct 2026): two separate tests, each run on its own and never combined: works (construction) cost +10% and a 6-month delay. The draft 15.45% transfer tax for non-EU buyers is not modelled as a cost absorbed by the project, because it would apply to the whole market and prices would adjust. No exit at old-stock prices is modelled: if units cannot be sold at renovated / new-build prices, they are held and let until they can be.
- A8 Hold-and-rent rent (owner parameter, 28 Oct 2026), matched to each scenarioA11: Average €16/m²/month (€928 per unit) and Premium €20/m²/month (€1,000 per 50 m² unit; owner: "€20+"). Sensitivity €16, €18 and €20/m² for both. Cross-checked with the xe.gr new-build median asking rent of ~€17.23/m²47: Average is below it, Premium above it and needs a design-led finish. All-homes central-Athens averages (~€12/m²,43,44) describe older stock and are not used. Asking rents, not agreed rents. Rent per unit = unit size (58 m² Average, 50 m² Premium) × rent.
- A9 Hold-and-rent cost and net-yield assumptions (both scenarios): no off-plan sales; development ends at completion and legal change of use (month 20), so IKE costs run 20 months and holding costs 17 months; sale-only costs dropped (2% marketing, unit sale documents, IKE and holding costs after completion); letting fee of one month's rent per unit at first let; for the net-yield sensitivity only, 5% vacancy, management and maintenance 10% of collected rent, building holding costs €12,000 a year and IKE running costs €6,000 a year, before tax. Partial case (sell 7 / hold 6): the 7 units are sold off-plan on the 24-month timeline; shared cost split pro rata by number of units. Gross ROI uses each scenario's own cost base and matched rent.
- A10 Off-plan sales and payment plan (owner parameter, 28 Oct 2026, modelled on Dubai-style off-plan plans): sales open when the construction permit is issued (month 6 in the base case). Buyers pay a 10% deposit at reservation (month 6), 10% at the preliminary sale agreement / SPA (month 7), 40% in equal monthly instalments during construction (months 6–17) and the final 40% at completion and final contracts (months 21–22). Collections are held by the project and reduce the equity needed; escrow / bank-guarantee protection for buyers and the Golden Visa timing of the final contract must be confirmed by Greek lawyers.
- A11 Matched scenarios (owner instruction, 28 Oct 2026): the study models two scenarios in which works budget, sale price and rent are matched to the same specification, so the project never builds at designer cost and sells at an average price. Average: works €1,100/m², 13 × 58 m² units at €250,000 (GV floor), rent €16/m². Premium: works €1,600/m², 15 × 50 m² units at €5,000/m² = €250,000, rent €20/m². Everything else is identical: purchase €1.2m, transfer tax 3.09%, basement €500/m², 24-month timeline, off-plan planA10, IKE €1,000/month, broker 2% of purchase price + 24% VAT, holding €1,000/month. Stress tests are run against each scenario's own baseA7.
- A12 Contingency (owner instruction, 28 Oct 2026): 12% of works incl. VAT is budgeted and paid in by investors during the works, and the base case treats it as fully spent (conservative). If it is not needed, the unspent amount is released to the IKE at the end of the project (month 24) and taxed as profit (22% corporate tax, 5% dividend withholding). Peak equity is the same in every contingency outcome, because the money is committed either way. Cases shown: fully spent (base), half spent, not needed. Because the unspent amount reduces total cost, it raises profit before tax by the full amount and net profit by about 74% of it (after 22% tax and 5% withholding, the same tax logic as the rest of the model).
- A13 ~210 m² unused building rights upside (not in the base case): the reported ~210 m² of unused building rights on the Metaxourgeio building42 (method of calculation not stated in the listing) is modelled as whole units of each scenario's size that fit in 210 m² (Average 3 × 58 m² = 174 m²; Premium 4 × 50 m² = 200 m²), at the scenario's own works cost per m², sale price €250,000 per unit, same purchase price and same 24-month timeline. Prerequisites: (1) the rights come from the plot's own zoning coefficient and height limit, not from New Building Code bonuses struck down by Council of State decisions 146–149/202515,49; (2) structural confirmation (our inference); (3) Golden Visa €250,000 eligibility of the extra units. The published rules extend that route to additions only for industrial and listed buildings50,51, so for a commercial building this is NOT confirmed and needs a lawyer's opinion or ministry confirmation; if not eligible, the €800,000 Athens threshold would apply21 and the units are not priced in this study. (4) The permit and works fit the timeline. The 25% / 50% / 75% probabilities are illustrative only; the real chance is known only after due diligence.
Image credit
Hero image: The Acropolis of Athens from Philopappos Hill — George E. Koronaios, Wikimedia Commons (CC0 1.0, public domain dedication).